|

First drink for the cattle at one of the new water troughs
|
Karamoja - Teso Water Development Programme. Uganda. 1994-1998
Aim and Location
In September 1990, following the civil war in Uganda, Christian
International Peace Service (CHIPS) was invited by local government
chiefs and church leaders to help stabilise the fragile peace between
the Karamojong and Itesot people. In 1992, because the water supply
situation in the area was particularly acute, CED was invited to advise
on the problem. A preliminary investigation concluded that a rural water
development programme would be an essential element in promoting the
resettlement of dispersed groups. Such a scheme was also seen as a
vehicle for fostering co-operation between the two tribes by them worked
together on water projects for their mutual benefit.
CED therefore designed a four-year water development programme of
which the principal elements were:
- 38 hand-dug shallow wells fitted with hand pumps.
- The rehabilitation of two earth dams (using ox-drawn dam scoops
for earth moving).
- The construction of a 14km long gravity piped water supply.
Joint funding for the scheme was obtained in April 1994.
Results
The work was completed by 1998 and was undertaken entirely by
community groups assisted by a few paid craftsmen, with technical
supervision and guidance being given by CED's Engineer working on site
in Uganda. The specific results were:
- Resettlement was enabled to proceed in the Kapelebyong, Achowa,
and Obalanga areas of Teso and at Apetolem, Iriri and Lamarotoiti in
Karamoja.
- Water was made available to 10,000 people.
- Up to 50% reduction of diarrhoea diseases and worm infestations
amongst communities.
- A reduction of guinea worm infection among the Karamajong of Iriri
was noted.
- A programme of pit latrine construction, remote from shallow well
sites, provided protection to the ground water resources.
- Women were particularly active in the local water committees and
benefited from improved family health and vitality, as well as
establishing a role for themselves in the councils of the community.
Following completion, shallow well construction and dam
rehabilitation has continued in the area, the methods and experience
gained from the project having allowed this replication of the scheme to
proceed.
Role of CED
CED was the design authority and provided technical advice and
supervision on site during implementation. CED entered into a Joint
Funding Agreement with the British Government's Department for
International Development (DFID), with matching funds being obtained
from other UK private sources. CED was the fund holder, accounting for
all expenditure, which was later audited.
Total Cost of Project
The Total cost of the project was €413,914 (£254,075).
Project Donors
| Donor |
€ |
£ |
| Department for International Development (DFID) |
173,618 |
106,573 |
| Methodist Relief & Development Fund (MRDF) |
64,757 |
39,750 |
| Comic Relief |
112,783 |
69,230 |
| Private Trust |
16,291 |
10,000 |
| CED's own resources |
10,685 |
6,559 |
| Numerous small donations |
35,780 |
21,963 |
| Totals |
413,914 |
254,075 |
|